|
|
|
|
 |
   |
 |
|
|
 |
Modern Pools
New pool construction Process.
Different pool designs require different procedures, but in general, the
Following phases should be what you expect when the new pool construction
starts. From start to finish, the whole process should take around 8 weeks.
Design Phase:
Our professional designers will work with you to come up with the best
possible design for your home. What you always envisioned.
The design is complete, includes landscaping, accessories like fire place or a fire
ring, Sod or artificial grass, decking, spa and water falls.
The Digging Phase:
After your are 100% satisfied with the design, we obtain permits from
engineering and the city. We also call digalert to mark any underground pipes.
On the designated start date, we mark the grounds, and set the leveling.
Our excavating team goes at it. This phase usually takes 1 day to complete.
Steel Rebar Phase.

Usually the next day after excavating, our steel rebar team goes to work.
|
|
Equipment, Plumbing, Gas and Electrical Phase:
|

This phase also usually takes 1 day to complete. |
|

Usually right after the steel rebar is installed, our team of plumbers and electricians start installing the water lines, electrical, gas and equipment lines. This phase usually takes 5 days to complete. |
|
Gunite/Shotcrete Phase:
As soon as the plumbing phase is completed, we call for inspection. Once the
inspection is signed off, the next day we shoot gunite or shotcrete.
This phase also usually takes 1 day to complete. We let the fresh gunite
Cure for 7 days.
Coping and Tile Phase:
After the pool has cured for 7 days, we start on the coping, then the tile. Depending
What kind of coping you choose, this process will take 3 to 5 days to complete. Concrete
Precast coping is shown below.
Decking Phase :
Once the coping and tile are done, we start preparing the deck. We install steel rebar
Bonding grid, drains and any other conduits, we call for pre-deck inspection, and proceed
With the decking process.
|
|
|
 |
|
Depending on the kind of deck you choose, installing the deck takes
2 to 5 days to complete. 5 piece interlocking paving stones are shown below.
Plaster Phase:
|
Once the deck is installed, we call for pre plaster inspection. Then we proceed with the plastering process. This takes 1 day to complete.
|
|
Once plaster is complete, we start filling the pool with water. Depending on the size of the pool, time needed to fill the pool varies.
|
 |
|
 |
|
The Enjoy Phase:
Need we say more.
|
|
 |
|
|
|